TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Brian Crawford, Municipal Services Director
PREPARED BY: Garrett Strang, Capital Projects Program Manager
SUBJECT:
title
Notice of Completion of the Alderwood Pickleball Courts Project, CIP No. 22042
end
ABSTRACT
Staff has deemed construction of the Alderwood Pickleball Courts Project, CIP No. 22042, to be substantially complete and recommends accepting the improvements and having the City Clerk record a Notice of Completion (NOC).
RECOMMENDATION
recommendation
Accept the improvements for the Alderwood Pickleball Courts Project, CIP No. 22042, as complete;
Direct the City Clerk or her designee to record a Notice of Completion and release bonds in accordance with State law and City Ordinances; and
Release any remaining retention from CIP No. 22042 in accordance with State law and City Ordinances.
body
PRIOR ACTION/VOTE
On June 3, 2025, the City Council approved Resolution No. 25-4836, approving the Capital Improvement Plan Budget for Fiscal Year 2025/26, and the Fiscal Year 2025/26 to 2029/30 Capital Improvement Plan, which included the Alderwood Pickleball Courts Project, CIP No. 22042 (Vote: 5-0).
On December 2, 2025, the City Council awarded the construction contract for the Alderwood Pickleball Courts Project, CIP No. 22042, to Micon Construction, Inc., in the amount of $307,628.60, plus a 15% contingency (Vote: 5-0).
STRATEGIC ALIGNMENT
This item aligns with the City Council goal of : coordinating and delivering responsive, effective community services relating to priority Tier 1. This Tier 1 project accomplishes the City Council goal of providing more pickleball courts for Murrieta residents.
DISCUSSION
Construction of the Alderwood Pickleball Courts Project, CIP No. 22042, began on January 12, 2026, and was deemed substantially complete by staff on April 1, 2026. The project consisted of improvements to Alderwood Park, including the construction of three (3) new pickle...
Click here for full text