TO: HONORABLE CHAIR AND COMMISSIONERS OF THE PARKS AND RECREATION COMMISSION
FROM: Lea Kolek, Parks and Community Service Manager
PREPARED BY: Roseann Otis, Office Assistant II - Parks & Recreation
SUBJECT:
title
July-August Parks, Projects, and Maintenance Report
end
RECOMMENDATION
recommendation
Receive and file.
body
PRIOR ACTION/VOTE
None.
CITY COUNCIL GOAL
Coordinate and deliver responsive, effective community services.
BACKGROUND
Special Projects, Construction, and Capital Improvement Plan Update
Library Expansion
* Library Construction Contract approved by Council on 8/19/25.
* Groundbreaking scheduled for 9/4/25 at 10:30 a.m.
* Construction is expected to start the third week of September.
Glen Arbor Dog Park
* Construction substantially completed 8/22/25.
* Ribbon cutting for the dog park was held on 8/25/25.
* Park is open to the public.
Los Alamos Hills Sports Park EV Charging Station
* Civil improvements on both the SCE and Customer side of meter have been completed by SCE forces.
* Staff are waiting for new meter installation and energizing by SCE, which is expected the first half of September.
* When energized, then City will have contractor install EV Chargers.
* Expecting completion by 10/1/25.
Alderwood Pickleball Courts
* Final plans are completed and providing contractor will plans and specifications for them to create a Job Order Contract Proposal.
* Expect to take to Council for contract award by 11/4/25, with construction to start by 12/1/25.
Cal Oaks Tennis Court Lighting
* Construction to start 9/10/25, expect completion by 10/1/25 (before end of daylight savings time).
Community Center Tennis Court Lighting:
* Scope of work is replacing the existing fixtures with compliant LED fixtures and adding a MUSCO subpanel to electrical so that lights can be scheduled and remotely controlled.
* Preparing construction contract to issue a PO to a contractor by 9/22/25.
* Once PO is issued, then the contractor will ...
Click here for full text