Title: Notice of Completion - Tot Lot Phase 1 Improvements
Attachments: 1. ATT 1 - Notice of Completion, 07.15.2025
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

FROM: Brian Crawford, Municipal Services Director

PREPARED BY: Brian Crawford, Municipal Services Director

SUBJECT:
title
Notice of Completion - Tot Lot Phase 1 Improvements
end


RECOMMENDATION
recommendation
Accept as complete the public improvements for the Tot Lot Phase 1 Improvement Project, Capital Improvement Project Nos. 22026, 22035, 22036, and 22038; and

Authorize the City Clerk to record a Notice of Completion and release bonds in accordance with State law and City ordinances.

body
PRIOR ACTION/VOTE
On July 2, 2024, the City Council awarded the construction contract for the Tot Lot Phase 1 Improvement Project, Capital Improvement Plan (CIP) Nos. 22026, 22035, 22036, 22038, to Millsten Enterprises, Inc., in the amount of $1,344,667,35, plus a 15% contingency (Vote: 5-0).

CITY COUNCIL GOAL
Coordinate and deliver responsive, effective community services.

DISCUSSION
The Community Services Department recently completed a project to replace equipment at two (2) park locations, Palomar Park and Oak Terrace Park; and construct brand new playground surfaces and install new equipment at three (3) locations: Oak Terrace Park (a new area for a large swing set), Monte Vista Park, and Northstar Park. Construction at these five (5) locations was Phase 1 of a broader Citywide tot lot replacement endeavor. Phase 2 included replacement of equipment at five (5) other parks and was completed in September 2024.

Construction consisted of grading, framing and pouring new Americans with Disabilities Act (ADA) compliant walkways and perimeter curbs, pouring concrete foundations for new equipment, assembly and installation of new tot lot equipment, and installing new engineered wood fiber play surface material. The park improvements will significantly increase the level of service for individuals and all children.

Mobilization for the project began on Monday, August 5, 2024, and construction activit...