File #: 23-301    Version: 1
Type: Consent Calendar Status: Agenda Ready
File created: 10/6/2023 In control: City Council
On agenda: 11/7/2023 Final action:
Effective date:    
Title: Notice of Completion for Traffic Signal Modification at Hancock Avenue and Milkwood Lane/Leafwood Drive
Attachments: 1. ATT 1 - Notice of Completion, 2. ATT 2 - Vicinity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

FROM: Bob Moehling, Director of Public Works

PREPARED BY: Jeff Hitch, City Engineer

SUBJECT: Notice of Completion for Traffic Signal Modification at Hancock
Avenue and Milkwood Lane/Leafwood Drive
title
end


RECOMMENDATION
recommendation
Accept the improvements for the Hancock Avenue and Milkwood Lane/Leafwood Drive traffic signal modification project, CIP No. 8257; and

Direct the City Clerk to issue and record a Notice of Completion and release bonds in accordance with State Law and City Ordinances; and release any remaining retention from CIP 8257 in accordance with State Law and City Ordinances.

body
PRIOR ACTION/VOTE
On August 2, 2022, the City Council awarded the contract for the construction of the traffic signal modification at the intersection of Hancock Avenue and Milkwood Lane/Leafwood Drive to the lowest responsible bidder, Alfaro Communications Construction, Inc., in the amount of $389,961.48 as part of the Citywide Signal Modifications Project, CIP No. 8257 (Vote: 5-0)1.

On August 15, 2023, the City Council conducted a public hearing and adopted Resolution No. 23-4699, approving Fiscal Year 2023/24 to Fiscal Year 2027/28 Capital Improvement Plan budget, which included the Citywide Signal Modifications Project, CIP No. 8257 (Vote: 5-0).

CITY COUNCIL GOAL
Plan, program and create infrastructure development.

BACKGROUND
On August 2, 2022, the City Council awarded the contract for the construction of the Hancock Avenue and Milkwood Lane/Leafwood Drive traffic signal modification project to Alfaro Communications Construction, Inc., in the amount of $389,961.48. The project installed protected left-turn phasing for the Hancock Avenue approaches to the intersection, split phasing for the Milkwood Lane and Leafwood Drive approaches to the intersection, and upgraded all pedestrian ramps. The purpose of the improvements was to enhance safety by adding prote...

Click here for full text