TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Bob Moehling, Director of Public Works
PREPARED BY: Garrett Strang, Civil Engineering Assistant
SUBJECT:
title
Acceptance of CalRecycle Rubberized Pavement Grant, Amend CIP Budget, and Appropriation of Funds
end
RECOMMENDATION
recommendation
Authorize the City Manager to accept the CalRecycle Grant No. TRP16-23-0020 award in the amount of $145,720 from the State of California Environmental Protection Agency;
Ratify execution of the grant agreement;
Amend the Fiscal Year 2023/24 Capital Improvement Plan Budget to appropriate an expenditure budget in CIP Project No. 13047; and
Amend the Fiscal Year 2023/24 Operating Budget to appropriate a grant revenue budget.
body
PRIOR ACTION/VOTE
On March 2, 2021, the City Council approved Resolution No. 21-4369, authorizing the submittal of applications for all CalRecycle grants for which the City of Murrieta is eligible (Vote: 4-0-1).1
On June 6, 2023, the City Council conducted a public hearing and adopted Resolution No. 23-4671, approving the Fiscal Year 2023/24 and 2024/25 Operating Budget (Vote: 4-0-1).2
On August 15, 2023, the City Council conducted a public hearing and adopted Resolution No. 23-4699, approving the Fiscal Year 2023/24 to Fiscal Year 2027/28 Capital Improvement Plan (CIP) budget, which included the Clinton Keith Road and Date Street Pavement Rehabilitation Project, CIP No. 13047 (Vote: 5-0).
CITY COUNCIL GOAL
Plan, program and create infrastructure development.
BACKGROUND
On August 29, 2023, City of Murrieta (City) staff submitted a grant application to the Department of Resources Recycling and Recovery (CalRecycle) as part of its Rubberized Pavement Grant Program, which provides reimbursement at the rate of $10 per ton of Rubberized Hot Mix Asphalt (RHMA) used on pavement rehabilitation projects. The City's upcoming pavement rehabilitation project, CIP No. 13047, will rehabilitate the pavement on Murrieta Hot Spring...