Skip to main content
Murrieta CA Logo
CITY OF
MURRIETA
File #: 25-1744    Version: 1
Type: Consent Calendar Status: Agenda Ready
File created: 10/31/2025 In control: Parks and Recreation Commission
On agenda: 11/18/2025 Final action:
Effective date:    
Title: Parks, Projects, and Maintenance Report
Attachments: 1. 10172025 Alderwood Tech Update, 2. 10232025 Alderwood Tech Update, 3. Park Ranger Monthly Report-August 2025, 4. Park Ranger Monthly Report-September 2025
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: HONORABLE CHAIR AND COMMISSIONERS OF THE PARKS AND RECREATION COMMISSION

FROM: Lea Kolek, Parks and Community Service Manager

PREPARED BY: Roseann Otis, Office Assistant II - Parks & Recreation

SUBJECT:
title
Parks, Projects, and Maintenance Report
end


RECOMMENDATION
recommendation
Receive and file.

body
PRIOR ACTION/VOTE
None.

CITY COUNCIL GOAL
Coordinate and deliver responsive, effective community services.

BACKGROUND
Special Projects, Construction, and Capital Improvement Plan Update

Los Alamos Hills Sports Park Electric Vehicle (EV) Charging Station
* Civil improvements on both the Southern California Edison (SCE) and customer side of meter have been completed by SCE forces and were inspected and accepted by the City.
* SCE meter is energized.
* Currently working on the Purchase Order (PO) to get stations installed. Expect that work to be completed by the end of November 2025.
Alderwood Pickleball Courts
* Project has been put out to bid with bid submittals due November 3, 2025.
* Barring high construction cost, staff expects to take construction contract to Council on December 2, 2025, with a construction start date by first half of January
California Oaks Sports Park Tennis Court Lighting
* Construction began last week now that correct light poles have been received.
* Expect full project completion by the end of November 2025.
Community Center Tennis Court Lighting
* Scope of work is replacing the existing fixtures with compliant light-emitting diode (LED) fixtures and adding a MUSCO Sports Lighting subpanel to electrical so that lights can be scheduled and remotely controlled
* Contract signed was signed on October 16, 2025.
* Preparing to issue a PO to a contractor by October 24, 2025.
* Once PO issued, then the contractor will order lights, which procurement could take one month.
* Staff is hopeful that installation may begin in December.
Sports Field Synthetic Turf Replacements at Los Alamos Hills Sports Park (LAHSP - ...

Click here for full text