BACKGROUND
Special Projects, Construction, and Capital Improvement Plan Update
Los Alamos Hills Sports Park Electric Vehicle (EV) Charging Station
* Civil improvements on both the Southern California Edison (SCE) and customer side of meter have been completed by SCE forces and were inspected and accepted by the City.
* SCE meter is energized.
* Currently working on the Purchase Order (PO) to get stations installed. Expect that work to be completed by the end of November 2025.
Alderwood Pickleball Courts
* Project has been put out to bid with bid submittals due November 3, 2025.
* Barring high construction cost, staff expects to take construction contract to Council on December 2, 2025, with a construction start date by first half of January
California Oaks Sports Park Tennis Court Lighting
* Construction began last week now that correct light poles have been received.
* Expect full project completion by the end of November 2025.
Community Center Tennis Court Lighting
* Scope of work is replacing the existing fixtures with compliant light-emitting diode (LED) fixtures and adding a MUSCO Sports Lighting subpanel to electrical so that lights can be scheduled and remotely controlled
* Contract signed was signed on October 16, 2025.
* Preparing to issue a PO to a contractor by October 24, 2025.
* Once PO issued, then the contractor will order lights, which procurement could take one month.
* Staff is hopeful that installation may begin in December.
Sports Field Synthetic Turf Replacements at Los Alamos Hills Sports Park (LAHSP - ...