File #: 26-1871    Version: 1
Type: Consent Calendar Status: Agenda Ready
File created: 2/6/2026 In control: City Council
On agenda: 3/3/2026 Final action: 3/3/2026
Effective date:    
Title: Finding that Emergency Conditions Persist in Connection with the Hayes Avenue Bridge at Miller Canyon Creek
Attachments: 1. ATT 1 - Resolution Continuing Hayes Avenue Bridge Emergency, 2. ATT 2 - Vicinity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

FROM: Bob Moehling, Public Works Director

PREPARED BY: Jeff Hitch, City Engineer

SUBJECT:
title
Finding that Emergency Conditions Persist in Connection with the Hayes Avenue Bridge at Miller Canyon Creek
end


RECOMMENDATION
recommendation
Adopt Resolution 26-4912, entitled: A Resolution of the City Council of the City of Murrieta, California, Declaring that Emergency Conditions Persist in Connection with the Hayes Avenue Bridge at Miller Canyon Creek.

body
PRIOR ACTION/VOTE
On July 1, 2025, the City Council adopted Resolution No. 25-4863, declaring that Emergency Conditions persist, appropriating funding, and approving the execution of a contract for reconstruction of the Hayes Avenue Bridge at Miller Canyon Creek (Vote 4-0).

On August 19, 2025, the City Council adopted Resolution No. 25-4882, declaring that Emergency Conditions persist in connection with the Hayes Avenue Bridge at Miller Canyon Creek (Vote 5-0).

On October 7, 2025, the City Council adopted Resolution No. 25-4891, declaring that Emergency Conditions persist in connection with the Hayes Avenue Bridge at Miller Canyon Creek (Vote 5-0).

On December 2, 2025, the City Council adopted Resolution No. 25-4899, declaring that Emergency Conditions persist in connection with the Hayes Avenue Bridge at Miller Canyon Creek (Vote 5-0).

On December 16, 2025, the City Council approved Amendment No. 1 to the Agreement with Contech Engineered Solutions for the additional amount of $130,500, to purchase a precase concrete arch-culvert system for the Hayes Avenue Bridge at Miller Canyon Creek (Vote 5-0).

CITY COUNCIL GOAL
Plan, program and create infrastructure development.

DISCUSSION
On February 6, 2025, staff encountered a pothole in the deck of the Hayes Avenue Bridge crossing Miller Canyon Creek, located generally between Ivy Street and B Street. Upon this discovery, Engineering staff believed the bridge could be unsafe and closed ...