TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Bob Moehling, Public Works Director
PREPARED BY: Bob Moehling, Public Works Director
SUBJECT:
title
Amendment to Agreement with Jacobs Engineering for Engineering Design Services for the Keller Road at I-215 Interchange Project, CIP No. 8449
end
RECOMMENDATION
recommendation
Approve Amendment No. 10 to the Engineering Design Services Agreement for the Keller Road at I-215 Interchange, CIP No. 8449, with Jacobs Engineering Group, Inc., revising the scope of work and reducing the total not to exceed contract amount by $279,448; and
Authorize the Mayor to execute the Amendment on behalf of the City.
body
PRIOR ACTION/VOTE
On April 6, 2010, the City Council adopted Resolution No. 10-2478 approving an agreement (Original Agreement) with Jacobs Engineering Group, Inc. in the amount of $377,795.64 to provide engineering and environmental services (Vote: 5-0).
On March 20, 2012, the City Council adopted Resolution No. 12-2885 approving an agreement (New Agreement) with Jacobs Engineering Group, Inc. in the amount of $361,243.45 to provide engineering and environmental services (Vote: 4-0).
On July 18, 2018, the City Council adopted Resolution No. 18-3952, approving Amendment No. 8 to the Design Engineering Services Agreement with Jacobs Engineering, Inc. (Vote: 5-0).
On April 7, 2020, the City Council adopted Resolution No. 20-4226, approving Amendment No. 9 to the Design Engineering Services Agreement with Jacobs Engineering Group, Inc. (Vote:5-0).
On June 3, 2025, the City Council adopted Resolution No. 25-4836, approving the Capital Improvement Plan budget for Fiscal Year 2024/25, and the Fiscal Year 2024/2025 to 2028/29 Capital Improvement Plan, which included the Keller Road at I-215 Interchange project, CIP No. 8449 (Vote: 5-0).
CITY COUNCIL GOAL
Plan, program and create infrastructure development.
DISCUSSION
The Keller Road at I-215 Interchange project, CIP 8449, is a top City inf...