TO: HONORABLE CHAIR AND COMMISSIONERS OF THE PARKS AND RECREATION COMMISSION
FROM: Lea Kolek, Parks and Community Service Manager
PREPARED BY: Roseann Otis, Office Assistant II - Parks & Recreation
SUBJECT: title
Parks, Projects, and Maintenance Report
end
RECOMMENDATION
recommendation
Receive and file.
body
PRIOR ACTION/VOTE
None.
CITY COUNCIL GOAL
Coordinate and deliver responsive, effective community services.
BACKGROUND
Special Projects, Construction, and Capital Improvement Plan Update
Library Expansion:
* Construction design package was submitted for second round of plan check.
* Anticipate bid package to be published in May.
* Goal is to break ground on construction by July/August 2025.
Town Square Parking Lot & Monument:
* Parking Lot has been completed.
* Monument has been completed.
* Electrical: Waiting for meters to be installed by SCE.
* Video Boards: Successful test run on one board. Troubleshooting connection to second board.
* Traffic Signal Control Cabinet Move: Waiting for SCE meter to make movement.
* Landscape: 95% completed.
Tot Lot Replacement Project, Phase 1, Gametime Equipment Sites:
* Monte Vista: Construction completed and park is open to the public.
* Northstar: Wrapping up equipment install after experiencing issues. Anticipate park will open first half of May.
* Palomar: Construction completed and park is open.
* Oak Terrace: Construction completed and park is open.
Glen Arbor Dog Park:
* Construction to start 4/23/25.
* Notifications have been sent to properties adjacent to park.
Los Alamos Hills Sports Park EV Charging Station:
* Design and construction of 9 head charging station being completed and paid for by SCE Charge Ready Program.
* Preconstruction meeting held 4/9/25.
* SCE to install meter pedestal week of 4/21/25.
* All construction (to be done by SCE contractor) on the City side of meter to be done in September 2025.
* Once improvements made and power is supplied to switchgear, then City wil...
Click here for full text