Effective date:    
Title: Collectible Work Authorization Agreement with Southern California Gas Company for the Murrieta Hot Springs Road Improvement Project, CIP No. 8079
Attachments: 1. ATT 1 - Collectible Work Authorization Agreement with the Gas Company, 2. ATT 2 - Vicinity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

FROM: Bob Moehling, Public Works Director

PREPARED BY: James Ozouf, Senior Civil Engineer, CIP

SUBJECT:
title
Collectible Work Authorization Agreement with Southern California Gas Company for the Murrieta Hot Springs Road Improvement Project, CIP No. 8079
end


RECOMMENDATION
recommendation
Approve a Collectible Work Authorization Agreement with Southern California Gas Company in the amount of $157,372.10 for improvements relating to the Murrieta Hot Springs Road Improvement Project, CIP No. 8079;

Authorize a fifteen percent (15%) construction contingency of $23,605.82; and

Authorize the City Manager to sign the Collectible Work Authorization Agreement.

body
PRIOR ACTION/VOTE
On September 6, 2022, the City Council approved a Collectible Work Authorization Agreement with Southern California Gas Company in the amount of $98,194.56, plus a fifteen (15%) contingency, for improvements relating to the Murrieta Hot Springs Road Improvement Project, CIP No. 8079 (Vote: 5-0).

On June 3, 2025, the City Council adopted Resolution No. 25-4836, approving the Fiscal Year 2025/26 to Fiscal Year 2029/30 Capital Improvement Plan budget which included the Murrieta Hot Springs Road Improvement Project, CIP No. 8079 (Vote: 5-0).

CITY COUNCIL GOAL
Plan, program and create infrastructure development.

DISCUSSION
The Murrieta Hot Springs Road Improvement project, CIP No. 8079, consists of numerous improvements to Murrieta Hot Springs Road between Margarita Road and Winchester Road. The roadway will be widened from a four-lane to a six-lane roadway between Via Princesa and Winchester Road. Other improvements include installation of raised medians, sidewalks, street lighting, retaining walls, and a traffic signal at Calle Del Lago. The widening will also impact private improvements such as the realignment of Via Frontera Road within the Ridgegate Community. The improvements will require relocation of various existing...