TO: HONORABLE CHAIR AND COMMISSIONERS OF THE PARKS AND RECREATION COMMISSION
FROM: Lea Kolek, Parks and Community Service Manager
PREPARED BY: Roseann Otis, Office Assistant II - Parks & Recreation
SUBJECT:
title
May-June Park, Projects, and Maintenance Report
end
RECOMMENDATION
recommendation
Receive and file.
body
PRIOR ACTION/VOTE
None.
CITY COUNCIL GOAL
Coordinate and deliver responsive, effective community services.
BACKGROUND
Special Projects, Construction, and Capital Improvement Plan Update
Library Expansion:
* Bid package published 6/13/25, bids due 7/14/25
* Completed mandatory bidder pre-bid job walk on 6/30/25
* Targeting August 19 for Council approval
* Goal is to break ground on construction by August/September 2025
Town Square Parking Lot & Monument:
* Taking Notice of Completion to Council in July.
Tot Lot Replacement Project, Phase 1, Gametime Equipment Sites:
* Taking Notice of Completion to Council in July.
Glen Arbor Dog Park:
* Taking request to increase contingency to 25% to Council on July 15. Unforeseen issues have resulted in larger than expected change orders.
* All grading is completed. Walkways have been poured.
* The dog park area is mainly complete.
* Construction phased to move back to top of slope.
* Driveways and parking lots to be completed by end of July.
Los Alamos Hills Sports Park EV Charging Station:
* Design and construction of 9 head charging station being completed and paid for by SCE Charge Ready Program.
* SCE Meter Pedestal construction completed.
* All construction (to be done by SCE contractor) on the City side of meter to be done starting July 14.
* Once improvements are made and power is supplied to switchgear, then the City will have our contractor install the EV chargers on SCE constructed pads and run wiring.
* Anticipate the chargers will be online by October 2025.
Los Alamos Hills Sports Park EV Charging Station:
* Design and construction of 9 head charging station being comple...