TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Bob Moehling, Director of Public Works
PREPARED BY: Garrett Strang, Civil Engineering Assistant
SUBJECT: Construction Contract for the Clinton Keith Road and Date Street
Pavement Rehabilitation Project, CIP 8043
title
end
RECOMMENDATION
recommendation
Award the construction contract for the Clinton Keith Road and Date Street Pavement Rehabilitation Project CIP No. 8043 to ONYX Paving Company, Inc. in the amount of $1,832,612.50;
Authorize a fifteen percent (15%) construction contingency of $274,891.88; and
Authorize the City Engineer to approve contract change orders not to exceed fifteen percent (15%) of the contract amount.
body
PRIOR ACTION/VOTE
On August 15, 2023, the City Council approved joint Resolution No. 23-4699, approving the Capital Improvement Plan Budget for Fiscal Year 2023/24 and the Fiscal Years 2023/24 to 2027/28 Capital Improvement Plan, which included the Clinton Keith Road and Date Street Pavement Rehabilitation Project, CIP No. 8043 (Vote 5-0).
CITY COUNCIL GOAL
Plan, program and create infrastructure development.
BACKGROUND
The Clinton Keith Road and Date Street Pavement Rehabilitation Project, CIP 8043, will rehabilitate the pavement on Clinton Keith Road from the western-most City boundary to Rancho Mirlo Road and Date Street from Margarita Road to 700 feet to the north-east (Attachment 1). Rehabilitation on Clinton Keith Road includes asphalt removal and replacement in designated areas and full-width roadway overlay with hot mix asphalt (HMA). Other activities include asphalt concrete dike improvements, overside drain replacement, miscellaneous concrete work, signing and striping, and loop detector replacement. Rehabilitation on Date Street includes asphalt removal and replacement in designated areas, half-width roadway pavement overlay with HMA, signing and striping, and loop detector replacement. CIP No. 8043 is funded ...