TO: HONORABLE CHAIR AND COMMISSIONERS OF THE PARKS AND RECREATION COMMISSION
FROM: Lea Kolek, Parks and Community Service Manager
PREPARED BY: Roseann Otis, Office Assistant II - Parks & Recreation
SUBJECT:
title
Parks, Projects, and Maintenance Report
end
RECOMMENDATION
recommendation
Receive and file.
body
PRIOR ACTION/VOTE
None.
CITY COUNCIL GOAL
Coordinate and deliver responsive, effective community services.
BACKGROUND
Special Projects, Construction, and Capital Improvement Plan Update
Library Expansion:
* Construction Design Package submitted for plan check on schedule on 1/30/25
* Pre-bid Council presentation planned for 3/18/25
* Anticipate bid package to be published by early May
* Goal is to break ground on construction by July/August 2025
Town Square Parking Lot & Monument:
* Construction began 11/14/24
* Parking Lot Location: drainage improvements and concrete work completed; parking lot just needs asphalt top which will be laid when landscape all surrounding improvements completed.
* Monument Location: CMU structure mostly complete; retaining wall completed; concrete sidewalks completed
* SCE Power Connection: trenches and conduit completed at both transformers. SCE connected power.
* Electrical: trenching for conduit to run power from parking lot panel to site lighting along back of city hall to monument to be completed by 2/14/25
* Video boards to be installed 2/13/25
Tot Lot Replacement Project, Phase 1, Gametime Equipment Sites
* Monte Vista: Construction substantially completed. Safety fencing will be installed by end of February, then park will open.
* Northstar: Experienced significant equipment fitment issues and ADA access issue that required custom equipment. On track to be completed by the end of February
* Palomar: Construction completed and park is open. New safety fencing will be installed in February.
* Oak Terrace: Construction substantially completed. Safety fencing will be installed by end of Feb and th...