Legislation Details

File #: 26-2111    Version: 1
Type: Consent Calendar Status: Agenda Ready
File created: 6/15/2026 In control: City Council
On agenda: 7/7/2026 Final action: 7/7/2026
Effective date:    
Title: Award Construction Contract for the Auto Mall, Date Street, and Hobie Circle Slurry Seal Project, CIP No. 13080, MSD Project No. 26-010
Attachments: 1. ATT 1 – Contract between the City of Murrieta and Roy Allan Slurry Seal, Inc., 2. ATT 2 – Proposal – Roy Allan Slurry Seal, Inc., 3. ATT 3 - Vicinity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                                                HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

 

FROM:                                           Brian Crawford, Municipal Services Director

 

PREPARED BY:                      Garrett Strang, Capital Projects Program Manager

 

SUBJECT:

title

Award Construction Contract for the Auto Mall, Date Street, and Hobie Circle  Slurry Seal Project, CIP No. 13080, MSD Project No. 26-010

end

ABSTRACT

The purpose of this item is to award the construction contract for the Auto Mall, Date Street, and Hobie Circle Slurry Seal Project to the lowest responsive and responsible bidder and find the project to be exempt from CEQA.


RECOMMENDATION

recommendation

Amend the Fiscal Year 2026/27 Capital Improvement Plan (CIP) Budget and establish an appropriation of $100,000 using Measure A Fund Unassigned Fund Balance into CIP No. 13080;

 

Find the Auto Mall, Date, and Hobie Slurry Seal Project, CIP No. 13080, MSD Project No. 26-010, to be exempt from CEQA and award the construction contract to Roy Allan Slurry Seal, Inc. in the amount of $79,665.72;

 

Authorize a 15% construction contingency of $11,949.86;

 

Authorize the Mayor to execute the construction contract; and

 

Authorize the Municipal Services Director and/or designee to approve contract change orders not to exceed fifteen percent of the contract amount.

 

body

PRIOR ACTION/VOTE

On June 3, 2025, the City Council approved Resolution No. 25-4836, approving the Capital Improvement Plan Budget for Fiscal Year 2025/26, and the Fiscal Year 2025/26 to 2029/30 Capital Improvement Plan, which included the Citywide Slurry Seal Project, CIP No. 13080 (Vote: 5-0).


STRATEGIC ALIGNMENT

This item aligns with the City Council goal to: aggressively pursue economic development relating to an administrative priority. This project will revitalize the subject streets by resurfacing the existing asphalt, in preparation to reconfigure the striping layout to allow more street parking for the local businesses.

 

DISCUSSION

The Auto Mall, Date, and Hobie Slurry Seal Project, CIP No. 13080, consists of striping removals, crack sealing, surface prep, street sweeping, traffic control, slurry sealing, and other ancillary work at Auto Mall Parkway, Date Street, and Hobie Circle. The intent of this project is to resurface and seal the subject streets in preparation for a revised striping configuration designed to increase the number of on-street parking spaces available for local businesses. Upon completion of the slurry seal work, the City's on-call striping contractor will install the new striping under separate contract. This project is funded utilizing Measure A (Fund 302).

The project includes slurry seal and other incidental work at the following locations:

                     Auto Mall Parkway from Jefferson Avenue to Date Street;

                     Date Street from Jefferson Avenue to Auto Mall Parkway; and

                     Hobie Circle from Auto Mall Parkway to Date Street.

 

Project Bidding and Determination

The City conducted an informal bid process per the requirements of the Murrieta Municipal Code for Public Works construction contracts between $75,000 and $219,999 and received a total of three (3) construction bids. The bid results are as follows:

 

Bidder

Proposal Cost

1.

Roy Allan Slurry Seal, Inc.

$79,665.72

2.

American Asphalt South, Inc.

$93,037.62

3.

NPG Asphalt

$165,665.00

 

Staff has reviewed the bids and determined that the item prices are consistent with today’s construction market. Staff recommends that the construction contract be awarded to the lowest responsible bidder, Roy Allan Slurry Seal, Inc., in the amount of $79,665.72, for the total proposal cost, plus a 15% construction contingency of $11,949.86, for a total of $91,615.58.

 

PUBLIC NOTICING

The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item).

 

CEQA AND REGULATORY OVERVIEW

 

Staff recommends exemption of this project from the California Environmental Quality Act (CEQA) pursuant to Section 15301 (Class 1 Categorical Exemption) of the CEQA Guidelines because this project involves “repair or maintenance” of existing infrastructure or facilities and is on the same site and serves the same purpose and capacity without expanded use.

 

FISCAL IMPACT

The total fiscal impact associated with the approval of this contract is $91,615.58, including the contingency. Staff recommends amending the Capital Improvement Plan Budget for Fiscal Year 2026/27 and establishing an appropriation of $100,000 using Measure A Fund Unassigned Fund Balance into CIP No. 13080.

 

The construction contract amount to be awarded is $79,665.72, plus an additional 15% contingency amount of $11,949.86, for a total not-to-exceed amount $91,615.58. Funding is available in CIP No. 13080 from Measure A (Fund 302).


ATTACHMENTS

ATT 1 - Contract between the City of Murrieta and Roy Allan Slurry Seal, Inc.

ATT 2 - Proposal - Roy Allan Slurry Seal, Inc.