BACKGROUND
Special Projects, Construction, and Capital Improvement Plan Update
Los Alamos Hills Sports Park Electric Vehicle (EV) Charging Station
• Civil improvements on both the Southern California Edison (SCE) and customer side of meter have been completed by SCE forces and were inspected and accepted by the City.
• SCE meter is energized.
• Currently working on the Purchase Order (PO) to get stations installed. Expect that work to be completed by the end of November 2025.
Alderwood Pickleball Courts
• Project has been put out to bid with bid submittals due November 3, 2025.
• Barring high construction cost, staff expects to take construction contract to Council on December 2, 2025, with a construction start date by first half of January
California Oaks Sports Park Tennis Court Lighting
• Construction began last week now that correct light poles have been received.
• Expect full project completion by the end of November 2025.
Community Center Tennis Court Lighting
• Scope of work is replacing the existing fixtures with compliant light-emitting diode (LED) fixtures and adding a MUSCO Sports Lighting subpanel to electrical so that lights can be scheduled and remotely controlled
• Contract signed was signed on October 16, 2025.
• Preparing to issue a PO to a contractor by October 24, 2025.
• Once PO issued, then the contractor will order lights, which procurement could take one month.
• Staff is hopeful that installation may begin in December.
Sports Field Synthetic Turf Replacements at Los Alamos Hills Sports Park (LAHSP - soccer only) and Torrey Pines baseball field
• Job Order Contract (JOC) received for both locations.
• Taking contract award to Council on November 4, 2025.
• Lead time for materials is four to six weeks.
• Staff anticipates construction to begin January 5, 2026
• Construction for LAHSP soccer field confined to January 5, 2026 to March 1, 2026 as the field is needed for league play.
Alderwood Technological Improvements
• The contractor continues to pull wire for the contactless access points, security cameras, and the audio/visual (AV) equipment.
• The contractor anticipates completion of the wire pulling by the first week of November.
• The AV contractor will follow the wire pulling contract to complete the installation of the AV equipment.
Flock Cameras for California Oaks Sports Park and Torrey Pines Park
• Council approved the order on September 16, 2025
• Order form signed by the City Manager.
• PO signed and a copy sent to Flock Cameras.
• Staff is waiting on updated insurance provisions from Flock Cameras.
• Revised deployment plan approved and an application made by Flock Cameras to the City for plan review.
California Oaks Sports Park - Graffiti and Vandalism Task Force
• Restroom Log - Completed. Park Rangers complete each day.
• Flock Camaras - Deployment plan in the City plan review process.
• Standard Operating Procedure (SOP) for Roles & Responsibilities, Patrols, Reporting and Documentation - Completed.
• California Oaks Sports Park Offsite Ranger/Public Safety Office - Outfitted and keys issued.
• Parks Maintenance:
o Completed all of the restroom doors and block wall extensions.
o Regarding the tree trimming or tree removal, staff is waiting for the Flock Cameras to be installed and then will determine which trees to trim and/or remove.
Parks Maintenance - Repairs, Inspections, Miscellaneous
• “Mini” Town Square Park turf renovation completed.
• Working toward a resolution on the insidious gopher and ground squirrel infestation at Hunt Park and the Youth Center “backyard.”
• Alta Murrieta Sports Park concession stand received a long-needed cleaning.
• Staff are putting together a team to update the interactive map on the City’s website.
• Maintenance staff continue to remove the old park rules signs with new ones that include the E-bike ordinance.
• The “bad” parking lot lights at Los Alamos Hills Sports Park have been removed and replaced.
FISCAL IMPACT
None.
ATTACHMENTS
1. Alderwood Park Clubhouse Technological Improvements Pictures