Title: Murrieta Hot Springs Road Pavement Rehabilitation Project, CIP No. 13047, EMWD Reimbursement Agreement
Attachments: 1. ATT 1 - Reimbursement Agreement Between the City and EMWD, 2. ATT 2 - Vicinity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                                                HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

 

FROM:                                           Bob Moehling, Public Works Director

 

PREPARED BY:                      Garrett Strang, Civil Engineering Assistant

 

SUBJECT:

title

Murrieta Hot Springs Road Pavement Rehabilitation Project, CIP No. 13047, EMWD Reimbursement Agreement

end

 

RECOMMENDATION

recommendation

Approve a Reimbursement Agreement with Eastern Municipal Water District (EMWD) and accept funding in the amount of $62,700 for adjustment of EMWD facilities as part of the Murrieta Hot Springs Road Pavement Rehabilitation Project, (CIP) Capital Improvement Plan No. 13047;


Amend the Fiscal Year 2024/25 CIP Budget to establish an additional appropriation in CIP No. 13047 for $62,700; and

 

Authorize the City Manager to execute the Reimbursement Agreement.

 

body

PRIOR ACTION/VOTE

On June 4, 2024, the City Council approved Resolution No. 24-4745, approving the Capital Improvement Plan Budget for Fiscal Year 2024/25, and the Fiscal Years 2024/25 to 2028/29 Capital Improvement Plan, which included the Murrieta Hot Springs Road Pavement Rehabilitation Project, CIP No. 13047 (Vote 5-0).

 

On September 3, 2024, the City Council approved the Construction Contract Award for the Murrieta Hot Springs Road Pavement Rehabilitation Project, CIP No. 13047, to Onyx Paving Company Inc (Vote 5-0).


CITY COUNCIL GOAL

Plan, program and create infrastructure development.

 

BACKGROUND

The Murrieta Hot Springs Road Pavement Rehabilitation Project, CIP No. 13047, will rehabilitate the pavement on Murrieta Hot Springs Road from Whitewood Road to Margarita Road. As part of the pavement rehabilitation process, Eastern Municipal Water District (EMWD) manholes and valve cans need to be adjusted to be even with the new roadway surface.

 

Staff negotiated a Reimbursement Agreement between the City and EMWD for the City’s contractor to adjust EMWD’s facilities during the City’s construction activities. The Agreement before the City Council today allows for up to $62,700 in facility adjustment expenses to be paid by EMWD. Staff recommends that the Capital Improvement Plan Budget be amended to include an appropriation of these funds into CIP Project No. 13047. The City will invoice EMWD for reimbursement of the funds at the conclusion of the Murrieta Hot Springs Road Pavement Rehabilitation Project CIP 13047.

 

FISCAL IMPACT

Staff recommends that the City Council establish a revenue budget for EMWD Reimbursement Funds in the amount of $62,700 and establish an expenditure appropriation into CIP 13047. Funds shall be allocated into Reimbursement Agreement Fund 319 (Revenue Code 3190060-42224 13047319-42224, Expenditure Code 3197500-70000 13047319-500).


ATTACHMENTS

1. Reimbursement Agreement between the City and EMWD

2. Vicinity Map