TO:                      HONORABLE CHAIR AND COMMISSIONERS OF THE PARKS AND RECREATION COMMISSION

 

FROM:                                           Lea Kolek, Parks and Community Service Manager

 

PREPARED BY:                      Roseann Otis, Office Assistant II - Parks & Recreation

 

SUBJECT:

title

Parks, Projects and Maintenance Report

end

 

RECOMMENDATION

recommendation

Receive and File.

 

body

PRIOR ACTION/VOTE

None.

 

CITY COUNCIL GOAL

Coordinate and deliver responsive, effective community services.

 

BACKGROUND

 

Special Projects, Construction, and Capital Improvement Plan Update

 

Library Expansion:

•                     Design development package was distributed to Development Review Committee (DRC) departments for comments due by 9/10/24.

•                     Graphic design firm finalized on 8/28/24 designs for frames for renderings and layouts, and donor takeaways for fundraiser being held 9/4/24.

•                     Goal is to break ground on construction by July 2025

 

Town Square Parking Lot & Monument:

•                     Bid opportunity was republished on 08/19/24 with changes to the bid schedule that reclassified some line items as additive bid items.

•                     New bids are due 9/9/24, which will provide ample time to evaluate bids and submit agenda report for the 10/15/24 Council meeting.

 

Tot Lot Replacement Project, Phase 2, LSI Equipment Site 

•                     Four of five park locations have been completed: Alta Murrieta, Firefighters, Eastgate, Rancho Acacias.

•                     Sycamore Park to be completed by first week of September.

•                     No major issues encountered.

•                     Staff is communicating progress via social media and updating CSD CIP web page.

•                     Staff is to take a change order for construction management consulting to Council for all sites on 10/1/24.

•                     Anticipated taking Notice of Completion to Council by 10/15/24.

 

Tot Lot Replacement Project, Phase 1, Gametime Equipment Sites 

•                     Two of four locations are currently in construction: Palomar Park (equipment swap) and Monte Vista Park (brand new playground construction).

•                     Staff sent construction notification letters to residents living around the parks on 7/19/24.

o                     Currently no feedback

 

Glen Arbor Dog Park

•                     Comments from Planning, Building and Safety were sent back to project team on 8/22/24.

o                     Staff will submit letter of exemption request for required electric vehicle spaces in new, 12-space parking lot.

•                     Landscape plan check is complete.

•                     Engineering plan check to be completed by 08/30/24.

•                     Goal is to publish bid no later than end of September 2024.

 

Los Alamos Hills Sports Park EV Charging Station

•                     Design and construction of nine-head charging station being completed and paid for by SCE Charge Ready Program.

•                     Once construction is completed, the City will install electric vehicle (EV) chargers on prepared pads and conduit.

•                     Southern California Edison (SCE) submitted plans to Building & Safetyand Engineering for approvals on February 5, 2024.

•                     Due to continued issues with supply chain and receiving electrical switch gear, SCE may not construct until end of 2024, or early 2025.

 

Community Center Tennis Court Lighting

•                     On hold until fixtures for California Oaks Sports Park tennis courts are selected by lighting design consultant so consistent fixtures will be used at both locations.

 

Firefighters Park Pickleball Courts

•                     In design, which will be completed by end of September (NV5).

 

Alderwood Pickleball Courts

•                     Processing purchase order for NV5; project to be in design by 9/1/24

•                     All American Rescue Plan Act (ARPA) funds have been committed

 

Cal Oaks Tennis Court Lighting

•                     Design starting by 8/1/24 (NV5).

 

 

 

Parks and Recreation Master Plan Update and Trails Master Plan

•                     Parks and Recreation Master Plan and Trails Master Plan draft reports are to be issued to senior staff for preliminary review the first week of September.

 

 

Parks Maintenance - Repairs, Inspections, Miscellaneous

 

•                     New picnic tables were delivered for Boys & Girls Club at Cal Oaks Sports Park.

•                     Field renovations have been completed.

•                     Maintenance staff has contracted with Busy Bee Electric to repair and replace the burned-out bulbs for the sports field and parking lot lighting at the sports parks.

•                     Maintenance staff has contracted with 24-Hour Express to repair the audio-visual cable trough at Town Square Park.

•                     Maintenance staff is looking for a rock to place the Rotary plaque for Murrieta Through Time.

•                     Maintenance staff is currently bidding the repair to the Ridder house roof at Equestrian Park.

•                     Maintenance staff is currently working on improving the drainage situation in and around the Mapleton tract.

•                     Maintenance staff is currently working on bidding the skate park fencing removal and replacement at California Oaks Sports Park.

 

 

 

FISCAL IMPACT

None.

 