File #: 24-692    Version: 1
Type: Consent Calendar Status: Agenda Ready
File created: 5/22/2024 In control: City Council
On agenda: 7/2/2024 Final action:
Effective date:    
Title: Construction Contract Tot Lot Improvement Project Phase 1
Attachments: 1. ATT 1 - Construction Contract & Proposal, Millsten Enterprises, Inc., Tot Lot Improvements, 07.2024
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                                                HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

 

FROM:                                           Brian Ambrose, Community Services Director

 

PREPARED BY:                      Brian Crawford, Senior Program Manager - Parks & Recreation

 

SUBJECT:

title

Construction Contract Tot Lot Improvement Project Phase 1

end

 

RECOMMENDATION

recommendation

Award the construction contract for the Tot Lot Improvement Project Phase 1, CIPs 22026, 22035, 22036, and 22038, to the lowest responsible bidder, Millsten Enterprises, Inc., in the amount of $1,344,667.35, plus a 15% contingency;

 

Authorize the Mayor to execute the agreement; and

 

Amend the Fiscal Year 2024/25 Capital Improvement Plan Budget to provide additional budget appropriation for CIPs 22026 and 22038.

 

body

PRIOR ACTION/VOTE

On May 16, 2023, the City Council approved Purchase Orders for Landscape Structures, Inc., Gametime, Michael Baker International, and Anser Advisory in the amount of $1,658,659 for the purchase of tot lot equipment, engineering design services, and project/construction management services, respectively (Vote: 5-0).


On August 15, 2023, the City Council adopted Resolution No. 23-4699, approving the Fiscal Years 2023/24 to 2027/28 Capital Improvement Plan (Vote: 5-0).


CITY COUNCIL GOAL

Coordinate and deliver responsive, effective community services.

 

BACKGROUND

The City of Murrieta (City) operates 53 parks, 32 of which have some form of tot lot playground equipment. As some of this infrastructure has been in place since the City’s founding, new equipment needs to be installed. This project will install new equipment at two (2) locations and construct access points and ramps to the play equipment that comply with current requirements for the Americans with Disabilities Act (ADA), which will significantly increase the level of service for individuals with disabilities. Additionally, completely new playgrounds will be constructed at three (3) of the four (4) locations where none exist today.

 

In late 2022, staff embarked on a project to design and construct the replacement of tot lot equipment at nine (9) locations. Due to the size of the project, staff separated these into two separate phases. The current phase applicable to this agenda report is for the four (4) tot lots at: Northstar Park, Monte Vista Park, Palomar Park, and Oak Terrace Park. Construction will involve grading, proper drainage, and pouring structurally required concrete footings and walkways, new tot equipment, and engineered wood chip play surfaces.

 

The City published the bid opportunity to PlanetBids on May 1, 2024, publicly advertised the Project in a regional newspaper on May 15, 2024, and again on May 25, 2024, and received three (3) construction bids on June 5, 2024, as follows:

 

Contractor

Base Bid

Additive Bid Items

Total Bid

Millsten Enterprises, Inc

$1,304,667.35

$40,000.00

$1,344,667.35

Cora Constructors, Inc

$1,415,057.50

$6,000.00

$1,421,057.50

R E Schultz Construction, Inc

$1,435,555.00

$10,000.00

$1,435,555.00

 

The bids were reviewed, and the item prices were determined to be consistent with today’s construction market. The additive bid items are for the purchase and installation of a sump basin to aid in rainwater drainage at one (1) of the tot lot locations if needed.

 

Staff recommends that the contract be awarded to the lowest responsible bidder, Millsten Enterprises, Inc., in the amount of $1,344,667.35, plus a fifteen percent (15%) contingency of $201,700.10, for a total contract amount of $1,546,367.45.

 

No bid protests were received for the Project.

 

FISCAL IMPACT

Staff requests the appropriation of additional funding from Park Developer Impact Fees
(Fund 133):

 

Location

CIP No.

Construction Budget*

Construction Bid**

Additional Funding Requested

Oak Terrace

22026

$130,000.00

$268,677.49

$138,677.49

Palomar

22035

$275,000.00

$215,860.75

$(59,139.25)

Northstar

22036

$600,000.00

$580,751.84

$(19,248.16)

Monte Vista

22038

$425,000.00

$481,077.37

$56,077.37

Totals

 

$1,430,000.00

$1,546,367.45

$116,367.45

 

*Estimated Remaining Available Construction Budget

**Construction Bid includes construction, additive bid items, and construction contingency amounts.

 

 

 

ENVIRONMENTAL IMPACT

Pursuant to Section 15303, New Construction or Conversion of Small Structures, Article 19. Categorical Exemptions, of the California Environmental Quality Act, this project is exempt as it consists of construction of limited numbers of new, small facilities or structures at locations already zoned for Parks.


ATTACHMENTS

1.                     Construction Contract & Proposal, Millsten Enterprises, Inc., Tot Lot Improvements, 07.2024