Legislation Details

File #: 25-1330    Version: 1
Type: Consent Calendar Status: Agenda Ready
File created: 3/20/2025 In control: City Council
On agenda: 4/15/2025 Final action:
Effective date:    
Title: Reimbursement Agreement with Eastern Municipal Water District for the Murrieta Hot Springs Road and Alta Murrieta Drive Intersection Project, CIP No. 13027
Attachments: 1. ATT 1 - EMWD Reimbursement Agreement, 2. ATT 2 - Vicinity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                                                HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

 

FROM:                                           Bob Moehling, Public Works Director

 

PREPARED BY:                      James Ozouf, Senior Civil Engineer, CIP

 

SUBJECT:

title

Reimbursement Agreement with Eastern Municipal Water District for the Murrieta Hot Springs Road and Alta Murrieta Drive Intersection Project, CIP No. 13027

end

 

RECOMMENDATION

recommendation

Approve a Reimbursement Agreement with Eastern Municipal Water District for relocation and adjustment of water and sewer facilities as part of the Murrieta Hot Springs Road and Alta Murrieta Drive Intersection Project, Capital Improvement Plan (CIP) No. 13027; and


Amend the Fiscal Year 2024/25 CIP Budget to establish an appropriation into CIP No. 13027 for $45,150, for the reimbursement funds.

 

body

PRIOR ACTION/VOTE

On June 4, 2024, City Council approved Resolution No. 24-4745, approving the Capital Improvement Plan Budget for Fiscal Year 2024/25, and the Fiscal Years 2024/25 to 2028/29 Capital Improvement Plan, which included the Murrieta Hot Springs Road and Alta Murrieta Drive Intersection project, CIP No. 13027 (Vote 5-0).


CITY COUNCIL GOAL

Plan, program and create infrastructure development.

 

BACKGROUND

The Murrieta Hot Springs Road at Alta Murrieta Drive Intersection project, CIP No. 13027, consists of constructing a 14-foot dedicated right-turn lane from eastbound Murrieta Hot Springs Road into the Murrieta Plaza entrance at Alta Murrieta Drive. The purpose of this improvement is to alleviate traffic congestion in the eastbound through lanes caused by motorists stacking up in the number three (3) through-lane planning to turn right and enter the Murrieta Plaza. The physical improvements are to begin just east of Caltrans’ right-of-way and the I-215 off-ramp.

 

As part of the planned improvements, it will be necessary to relocate or adjust Eastern Municipal Water District (EMWD) facilities to accommodate the new turn pocket. The facilities include an underground pressure-reducing station, a water meter, a water backflow device, and a sewer manhole. The pressure-reducing station is located on private property within an EMWD easement and will be the City’s financial obligation to relocate. The remaining EMWD facilities are located within City right-of-way and will be EMWD’s financial responsibility. EMWD is seeking to have the relocation of its facilities completed by the City’s contractor. Staff recommends combining the EMWD relocations with the City’s construction activities to minimize the impacts on the traveling public.

 

The reimbursement agreement addresses the City’s requirement to relocate the pressure-reducing station at the City’s expense as well as EMWD’s reimbursement to the City for the remaining facilities to be relocated. The amount is summarized as follows:

 

EMWD Responsibility

Manhole, Water Meter, Backflow Relocation

$45,150

City Responsibility

Pressure Reducing Station Relocation

$120,660

 

Staff recommends that CIP 13027 be amended to include an appropriation of $45,150. The City will invoice EMWD for reimbursement of the funds at the conclusion of the project. The City’s responsible portion of the reimbursement agreement will be handled by the City’s direct payment to the contractor.

 

FISCAL IMPACT

Staff recommends that City Council amend the Fiscal Year 2024/25 CIP Budget to establish an appropriation of $45,150 into CIP No. 13027 for reimbursement funds and establish a reimbursement account to process reimbursement payments from EMWD in the amount of $45,150 through CIP Account No. 3197500/13027319-500.

 

The City is responsible for an estimated amount of $120,660. Sufficient funding is available in CIP 13027.


ATTACHMENTS

1. EMWD Reimbursement Agreement

2. Vicinity Map