Title: Award a Contract to Hi-Top Roof, Inc. for Installation of a Silicone Roofing Application for City Hall
Attachments: 1. ATT 1 - HI-Top Roof Inc. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                                                HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

 

FROM:                                           Justin Clifton, City Manager

 

PREPARED BY:                      Bryce Wilson - Management Analyst

 

SUBJECT:

title

Award a Contract to Hi-Top Roof, Inc. for Installation of a Silicone Roofing Application for City Hall

end

 

RECOMMENDATION

recommendation

Award a contract to Hi-Top Roof, Inc. for the installation of a Silicone Roofing Application for the City of Murrieta City Hall Roof Repair Project, Capital Improvement Project (CIP) No. 10027, in the amount of $155,000, plus a fifteen percent (15%) contingency; and


Authorize the City Manager to execute the agreement and other related documents.

 

body

PRIOR ACTION/VOTE

On August 16, 2022, the City Council adopted Resolution No. 22-4601, approving the Fiscal Year 2022/23 Capital Improvement Plan (CIP) Budget and approving the Fiscal Years 2022/23 to 2026/27 Capital Improvement Plan (Vote: 5-0).


CITY COUNCIL GOAL

Plan, program and create infrastructure development.

 

BACKGROUND

The City Hall roof is over 17 years old and shows signs of long-term wear and tear. Industry standards suggest replacing the roof every 12-20 years. Over the years, the rooftop has developed several leaks that become evident even during small weather events. In 2018, the City Council recognized that the roof was nearing the end of its life span and dedicated a Capital Improvement Project (CIP) to replace it. In Fiscal Year 2022/23, the City Council approved an appropriation of $202,000, to repair the City Hall roof (CIP No. 10027).

 

On January 28, 2025, the City publicly advertised a notice inviting bids for the installation of a Fluid-Applied Roofing (FAR) System for City Hall. This is a type of roof coating in which a liquid silicone membrane is applied directly onto an existing roof surface, creating a seamless, waterproof layer that protects the roof without requiring a complete removal and replacement.

 

A total of 17 potential bidders attended the pre-bid walk-through on February 13 and 18, 2025. On February 26, 2025, 14 vendors submitted bid proposals. For this type of project, the City is required to select “the lowest responsible bidder,” which in this case is Hi-Top Roof, Inc. Staff has reviewed Hi-Top Roof, Inc.'s license and insurance and found them to be in good standing. Therefore, staff recommends awarding a contract to Hi-Top Roof, Inc. The bids received ranged from $155,000 - $482,471.

 

The table below summarizes the bids received:

 

Company Name

Bid Amount

Hi-Top Roof, Inc.

$155,000.00

Solar Roofing and Energy Storage

$169,900.00

Pacific Polymers Inc. DBA American Foam Experts

$171,618.00

Bell Roof Co

$179,700.00

Rainy Day Roofing

$185,545.26

AOS Inc. dba Superior Roofing

$194,940.00

Best Contracting Services, Inc.

$199,760.00

A Good Roofer Inc

$201,038.00

Universal Coatings Inc

$217,100.00

Brazos Urethane, Inc.

$219,750.00

Danny Letner Inc. dba/Letner Roofing Co.

$240,534.00

Chambers Inc.

$260,725.00

Sylvester Roofing

$282,400.00

Rite-Way Roof Corporation

$482,471.00

 

The agreement with Hi-Top Roof, Inc. includes roofing services and the application of a fluid-applied silicone roofing system for an amount not to exceed $155,000, plus a 15% contingency,  bringing the total contract value to $186,000.

 

FISCAL IMPACT

Funding is available in CIP No. 10027.


ATTACHMENTS

1.                     Hi-Top Roof, Inc. Agreement