File #: 24-489    Version: 1
Type: Discussion Status: Agenda Ready
File created: 2/23/2024 In control: City Council
On agenda: 3/19/2024 Final action:
Effective date:    
Title: Construction Contract for the Clinton Keith Road and Date Street Pavement Rehabilitation Project, CIP 8043
Attachments: 1. ATT 1 - Vicinity Map, 2. ATT 2 - Contract between the City of Murrieta and ONYX Paving Company, Inc., 3. ATT 3 - Proposal from ONYX Paving Company, Inc., 4. ATT 4 - Bid Summary, 5. ATT 5 - Received After Agenda Printed - Presentation

TO:                                                                HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

 

FROM:                                           Bob Moehling, Director of Public Works

 

PREPARED BY:                      Garrett Strang, Civil Engineering Assistant

 

SUBJECT:                                          Construction Contract for the Clinton Keith Road and Date Street
                                 Pavement Rehabilitation Project, CIP 8043

title

end

 

RECOMMENDATION

recommendation

Award the construction contract for the Clinton Keith Road and Date Street Pavement Rehabilitation Project CIP No. 8043 to ONYX Paving Company, Inc. in the amount of $1,832,612.50;

 

Authorize a fifteen percent (15%) construction contingency of $274,891.88; and

 

Authorize the City Engineer to approve contract change orders not to exceed fifteen percent (15%) of the contract amount.

 

body

PRIOR ACTION/VOTE

On August 15, 2023, the City Council approved joint Resolution No. 23-4699, approving the Capital Improvement Plan Budget for Fiscal Year 2023/24 and the Fiscal Years 2023/24 to 2027/28 Capital Improvement Plan, which included the Clinton Keith Road and Date Street Pavement Rehabilitation Project, CIP No. 8043 (Vote 5-0).

 

CITY COUNCIL GOAL

Plan, program and create infrastructure development.

 

BACKGROUND

The Clinton Keith Road and Date Street Pavement Rehabilitation Project, CIP 8043, will rehabilitate the pavement on Clinton Keith Road from the western-most City boundary to Rancho Mirlo Road and Date Street from Margarita Road to 700 feet to the north-east (Attachment 1). Rehabilitation on Clinton Keith Road includes asphalt removal and replacement in designated areas and full-width roadway overlay with hot mix asphalt (HMA). Other activities include asphalt concrete dike improvements, overside drain replacement, miscellaneous concrete work, signing and striping, and loop detector replacement. Rehabilitation on Date Street includes asphalt removal and replacement in designated areas, half-width roadway pavement overlay with HMA, signing and striping, and loop detector replacement. CIP No. 8043 is funded by the Road Repair and Accountability Act of 2017 (SB-1), Measure A and Gas Tax.

 

Project Bidding and Determination

The City advertised the project on January 18, 2024, and received nine construction bids on February 15, 2024. The bid results are as follows:

Bidders                                                                                                                              Bid Amounts

1.                     ONYX Paving Company, Inc.                                                                                    $1,832,612.50

2.                     LC Paving & Sealing, Inc.                                                                                    $1,869,362.15

3.                     Vance Corporation                                                                                                         $1,903,503.96

4.                     ATP General Engineering Contractors,                     $1,926,721.20
a Division of Martic Marietta SD Aggs, LLC

5.                     All American Asphalt                                                                                                         $1,944,944.00

6.                     R.J. Noble Company                                                                                                         $2,030,499.40

7.                     Eagle Paving Company, Inc. dba Toro Engineering                     $2,064,000.00

8.                     LCR Earthwork & Engineering, Corp.                                                               $2,147,212.55

9.                     Hardy & Harper, Inc.                                                                                                         $2,310,409.14

The Department of Public Works/Engineering has reviewed the bids and determined that the item prices are consistent with today’s construction market and recommends that the Contract be awarded to the lowest, responsible bidder, ONYX Paving Company, Inc., in the amount of $1,832,612.50 for the Total Base Bid, plus a fifteen percent (15%) contingency of $274,891.88, for a total of $2,107,504.38 (Attachments 2-4). The City Engineer will be authorized to approve Contract Change Orders not to exceed fifteen percent (15%) of the Contract amount.

FISCAL IMPACT

The proposed contract amount to be awarded is $1,832,612.50, plus an additional fifteen percent (15%) contingency amount of $274,891.88, for a total of $2,107,504.38. Funding is available in CIP 8043.

 

ATTACHMENTS

1.                     Vicinity Map

2.                     Contract between the City of Murrieta and ONYX Paving Company, Inc.

3.                     Proposal from ONYX Paving Company, Inc.

4.                     Bid Summary