Title: Notice of Completion – City Hall and Murrieta Police Department Parking Lot Resurfacing Project, MSD Project No. 26-004
Attachments: 1. ATT 1 - Notice of Completion
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

FROM: Brian Crawford, Municipal Services Director

PREPARED BY: Garrett Strang, Capital Projects Program Manager

SUBJECT:
title
Notice of Completion – City Hall and Murrieta Police Department Parking Lot Resurfacing Project, MSD Project No. 26-004
end
/
ABSTRACT
Staff has deemed construction of the City Hall and Murrieta Police Department (PD) Parking Lot Resurfacing Project, Municipal Services Department (MSD) Project No. 26-004, to be substantially complete and recommends accepting the improvements and having the City Clerk record a Notice of Completion (NOC).

RECOMMENDATION
recommendation
Accept the improvements for the City Hall and PD Parking Lot Resurfacing Project, MSD Project No. 26-004, as complete;

Authorize the City Clerk to record a Notice of Completion; and

Direct the Municipal Services Department to release bonds in accordance with State law and City ordinances.

body
PRIOR ACTION/VOTE
On July 7, 2026, the City Council approved Resolution No. 26-4962, approving the Capital Improvement Plan Budget for Fiscal Year 2026/27, and the Fiscal Year 2026/27 to 2030/31 Capital Improvement Plan. (Vote: 4-0-1)

STRATEGIC ALIGNMENT
This item aligns with the City Council goal to plan, program and create infrastructure development. This project aims to continue preventative maintenance to prolong the lifespan of City owned infrastructure assets.

DISCUSSION
In April 2026, a Public Works Construction Contract was awarded to NPG, Inc., to resurface the City Hall and Police Department front parking lots. The work performed consisted of crack filling, application of a seal coat, and restriping of both parking lots. The project was undertaken to preserve and extend the service life of the existing pavement, protect the asphalt from further deterioration, and restore pavement markings to improve safety, visibility, and overall functionality for City staff and visitors.

The City Hall and PD Parking ...

Click here for full text