Title: Development Plan Permit 2023-00027 and Conditional Use Permit 2024-00028 for a Repair and Maintenance, Motor Vehicles use type, MTA Tire Shop
Attachments: 1. ATT 1 - PC Reso DP-2023-00027-CUP-2023-00028 9.11.pdf, 2. Exhibit A (Draft COAs) DP, 3. Exhibit B (Draft COAs) CUP, 4. Exhibit C - Statement of Operations (MTA), 5. ATT 2 - Vicinity Map (color), 6. ATT 3 - Staff Report (MTA) 7.24.24, 7. ATT 4 - MTA Project Site Plan, 8. ATT 5 - Notice of Exemption (Draft) - DP-2023-00027 & CUP-2024-00028, 9. ATT 6 - PWQMP, 10. ATT 7 - MTA Drainage Report 202404, 11. ATT 8 - Noise Report (Original)
TO: HONORABLE CHAIR AND MEMBERS OF THE PLANNING
COMMISSION

FROM: Carl Stiehl, City Planner

PREPARED BY: Roderick Salazar, Assistant Planner

SUBJECT:
title
Development Plan Permit 2023-00027 and Conditional Use Permit 2024-00028 for a Repair and Maintenance, Motor Vehicles use type, MTA Tire Shop
end


RECOMMENDATION
recommendation
1. Determine that the Project is exempt from the California Environmental Quality Act (CEQA) as an in-fill development project pursuant to Section 15332 of Title 14, Division 6, Chapter 3 of the California Code of Regulations (CEQA Guidelines); and

2. Approve A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF MURRIETA APPROVING DEVELOPMENT PLAN (DP) 2023-00027, CONDITIONAL USE PERMIT (CUP) 2024-00028, FOR THE CONSTRUCTION AND OPERATION OF A REPAIR AND MAINTENANCE, MOTOR VEHICLES, USE WITH A 4,995 SQ. FT. STRUCTURE, PARKING, LIGHTING, LANDSCAPING, TRASH ENCLOSURE, AND ASSOCIATED IMPROVEMENTS ON PROPERTY LOCATED ALONG MADISON AVENUE (APN: 910-490-015), based on the Findings and subject to the Conditions of Approval in Exhibits A, and B, and the Statement of Operations in Exhibit C (see Attachment 1).

body
PRIOR ACTION/VOTE

On July 24, 2024, the Planning Commission continued this project at the Applicant's request to August 14, 2024 (Vote: 4-0). On August 14, 2024, the Planning Commission continued this project at the Applicant's request to September 11, 2024 (Vote: 4-0).

BACKGROUND
On July 24, 2024, staff presented a proposed project of a Development Plan and Conditional Use Permit to construct and operate a 4,995-square-foot auto and tire repair shop with a mezzanine and six service bays. The project additionally provides associated parking, landscaping, and a trash enclosure on a 0.68-net acre site. Prior to the July 24 Planning Commission Hearing a comment letter from a representative of a neighboring property requesting a continuance in order to have time to review the pr...