TO: HONORABLE CHAIR AND COMMISSIONERS OF THE PARKS AND RECREATION COMMISSION
FROM: Lea Kolek, Parks and Community Service Manager
PREPARED BY: Roseann Otis, Office Assistant II - Parks & Recreation
SUBJECT:
title
Parks, Projects, and Maintenance Report
end
RECOMMENDATION
recommendation
Receive and file.
body
PRIOR ACTION/VOTE
None.
CITY COUNCIL GOAL
Coordinate and deliver responsive, effective community services.
BACKGROUND
Special Projects, Construction, and Capital Improvement Plan Update
Sykes Ranch Park Historic Elements:
* Construction was substantially completed by April 5, 2024.
* Notice of Completion went to Council on May 7, 2024.
Glen Arbor Park - Dog Park Feature:
* 100% plans and estimate submitted by MBI.
* Cost estimate is higher than budget, evaluating value engineering strategies at this time, including possible removal of parking lot.
* The goal is to publish the bid no later than the end of August 2024.
Tot Lot Replacement Project, Phase 2, LSI Equipment Site
* Construction to begin June 10, 2024.
Tot Lot Replacement Project, Phase 1, Gametime Equipment Sites
* Bid published May 1, 2024, due June 5.
* Construction contract to Council for approval on July 2, 2024.
Town Square Parking Lot & Monument
* Final draft of plans and bid documents being reviewed.
* Preparing bid packet for publication.
* Bid to be posted no later than June 17 to be due July 15, for contract approval August 20.
Los Alamos Hills Sports Park EV Charging Station
* Design and construction of nine head charging stations being completed and paid for by SCE Charge Ready Program.
* Once construction is completed, then City will install EV chargers on prepared pads and conduit.
* SCE submitted plans to Building & Safety, Engineering for approvals February 5, 2024.
* Due to continued issues with supply chain getting electrical switch gear, SCE may not construct until end of 2024, or early 2025.
Community Center Tennis Court Lightin...