Title: Parks, Projects, and Maintenance Report
TO: HONORABLE CHAIR AND COMMISSIONERS OF THE PARKS AND RECREATION COMMISSION

FROM: Lea Kolek, Parks and Community Service Manager

PREPARED BY: Roseann Otis, Office Assistant II - Parks & Recreation

SUBJECT:
title
Parks, Projects, and Maintenance Report
end


RECOMMENDATION
recommendation
Receive and file.

body
PRIOR ACTION/VOTE
None.

CITY COUNCIL GOAL
Coordinate and deliver responsive, effective community services.

BACKGROUND
Sykes Ranch Park Historic Elements:
* Construction substantially completed by April 5, 2024; punch list is being resolved.
* Taking Notice of Completion to City Council on May 7, 2024.
Glen Arbor Park - Dog Park Feature:
* Preliminary design completed.
* Sixty percent Plan submittal with Engineering for review.
* Landscape design firm working on progress for final design.
* Preparing bid packet for publication.
* Anticipate publishing by May 2024.
Tot Lot Replacement Project, Phase 2, LSI Equipment Site
* Three bids were received on April 10, 2024.
* Construction contract will go to Council by May 7, 2024.
Tot Lot Replacement Project, Phase 1, Gametime Equipment Sites
* Bid packets and exhibits are complete.
* Structural calculation packages approved by Building & Safety.
* Engineering reviewing final plan set.
* Anticipate putting out to bid by May 1, 2024.
Town Square Parking Lot & Monument
* Final draft of plans and bid documents being reviewed.
* Preparing bid packet for publication.
* Bid to be posted by end of May.
Los Alamos Hills Sports Park EV Charging Station
* Design and construction of nine head charging stations being completed and paid for by SCE Charge Ready Program.
* Once construction is completed, then City will install EV chargers on prepared pads and conduit.
* SCE submitted plans to Building & Safety, Engineering for approvals February 5, 2024.
* Due to continued issues with supply chain getting electrical switch gear, SCE may not construct until end of 2024, or early 2025.
Commu...